All the previous blog posts covered work that was done in the first week of work. We assumed that since the weather is so lousy and wet this week, that not much would get done. But we were wrong! The men want to get the foundation in so that the out-of-work carpenters can get started building the house. They are all appreciative to be working right now.
This blog post will cover the installation of the forms. Unlike when the footings were made, which used the excavated earth as a "form" to hold the concrete, the walls of the foundation use forms made out of boards. These boards are held together with fasteners. This first photo shows the blue guide line on which the forms will align to make the wall.
Here you can see the forms as seen from the Eddie and Park door. You can see inbetween the inside and outside pieces of board. There is more rebar in there to reinforce the concrete once it is poured.