Monday, November 30, 2009

Raising the Roof

Last week I mentioned that there was video of the truss on the gabled end of the house being raised up into position. Well, here it is! This was taken the day before Thanksgiving.

These roof trussses are huge triangles made of wood. They are manufactured off-site and delivered as a group. We are still a little curious how they got them all up there on the roof.

What you will see in the video is a construction worker getting into position on the back corner of the house. Another man was in the same position on the front side. Then, two other men used a 2x4 and muscle power to push it up into the air, pivoting it into place.

Go ahead and click on the little play triangle below the black box. And be sure your sound is turned on.

Workers everywhere!

Today is the beginning of week four. The old stairs to the attic were demolished, leaving quite a view from the old to the new portions of the house. Here Duncan is standing in the old hallway next to the bathroom. Behind him are some temporary planks laid down to span the hole where the stairs to the attic used to be.


Also being worked on today is the plumbing. Here are a variety of PVC pipes coming up into their locations in the new powder room and laundry room. The next photo shows the plumbers rolling out copper tubing for clean water supply lines.





Finally, the entire roof of the addition and the existing house were installed today. Here is the view from Eddie and Park Rd.

Saturday, November 28, 2009

Floorplan drawing




This is the floorplan for the first floor. I made it using a freely downloaded program called Envisioneer Express. Some of you children may enjoy using it yourself!
The top of the drawing is where the back yard is located.
The left half is where the original house is, and the right half is a proposed future garage.
What you have in the middle is a 30x32 foot addition. The rooms are bedroom, dining room, living room, entry, mudroom, hallway to side yard, powder room, laundry.
Feel free to ask any questions about what you see here.

Week Three

Whew! The construction men are so fast at what they do, it has been hard to keep this blog current. I last left you with a beam and some walls going up. You won't believe what it looks like 3 work days later! (See Chad and Zoe?)


But let me back up and show you how it got to that point.
First, the rest of the first floor walls were built and lifted into place.



Then,the joists were laid on that center beam and the walls. These will hold up the second floor. Here is the view from underneath the joists, looking up through the floor. Later on this day, the entire second floor sub-floor will be laid on these joists.


Next came walls for the second story. Notice in the photo how the first floor rooms are now in shadows, because there is a floor above them.



Here is the view from Eddie and Park and Peachtree. We are thinking that the
tree touching the house needs to come down. It seems to be leaning in the direction of the house, and touches it already. It doesn't seem like it would be wise to leave it there, but taking out another tree is such a shame.


Next came the roof trusses. We were on our way out of town Wednesday morning and went by at 8:45 a.m. By the time we got there, they already had all the trusses lifted up onto the top of the house and were halfway done attaching them!! I won't show a photo of this right now, because I want to add a video (some other time) of the gable-end truss being raised into place.


By the end of the day, they had finished attaching all those trusses, as you can see in this next photo. The little window there is the bathroom tilt-in window for ventilation.



Here is a look at the inside of the dormer that was made to give proper headroom to the stairs. The dark part you are looking in to is the attic of the original house. The rest of the photo shows the new wall studs that will separate the stairwell off from the attic. If you could look down you would see the stairs.



And, drumroll please.... here is the great view from the school room. WOW!!!!!


Friday, November 20, 2009

First floor walls up

Today is Friday, the end of the second week of work on our addition. Wow! What a LOT has happened in just a few days.

The biggest item we noticed as we arrived is the presence of another wall and a huge beam going across from the original house to this new wall. Wow! That beam is what the second floor joists will be resting on. One end of each joist will be on the beam and the other end on the front wall or the back wall, as the case may be.


Here is the stack of joists waiting for next week. Also in the photo is the stack of flooring for the second floor.



In this photo, you are seeing the workmen making a wall. They are building it as it lays on the ground. Then they will lift it up in to place.



If you look carefully, you will notice that a hole is being drilled into the bottom edge of this section of wall. Sticking out of the concrete foundation are metal pins every yard or so. When the men stand the wall up, these holes will fit over the pins, keeping it from sliding off of its foundation wall. Pretty cool.



Here is video of the wall being lifted up into place!


Thursday, November 19, 2009

What a surprise!

Since we went by yesterday and saw the forms being put into place, we didn't think much would be happening. Again, we were wrong! They must have called the concrete truck to come yesterday afternoon, because already today the forms were taken down and some walls were put up! We didn't see any of this happening, but grabbed a photo tonight. Hopefully we'll see some action tomorrow! How exciting.

This photo is taken from the back yard looking toward the family room. The railing seen here is the one that is by the outside stairs that go down to the basement. The black openings in the walls are where windows will be looking out from the family room into the backyard.

Wednesday, November 18, 2009

Exterior house colors

For anyone interested to know, we have chosen our exterior house colors. The siding is by Certainteed. It is insulated siding in the color "Cypress". The trim will all be white. The roof will be a dark charcoal color. The following photo will give you an idea of how it will look, though the house in the photo is NOT our house! Basically, cypress is a soft green color. We think that it will look serene in the park-like setting that is Pipkin Place. We chose a dark roof and white windows to provide some contrast to the soft overall color. Remember in your comments that the materials have already been ordered--- so don't say anything bad! hee hee hee!


There's a hole in the basement, dear Liza!

Another piece of work that was accomplished this week is making a hole in the basement floor. Why would that be a good thing, you ask? Well, in order to properly support the new staircases and their new walls and the bump-out dormer in the roof which allows code-approved headroom.... it is necessary to add another beam in the basement that runs parallel to the existing one. Now, this new one will not run the length of the house as does the old one. It will just be to support the new walls and roof around the staircases.
The beam will sit on posts, and those posts will sit on.... can you guess? ..... Footings! Just like the outside trenches, the footings in the basement will use excavated earth for their forms. But where is earth in the basement? Under the floor, of course! While producing MUCH dust, the floor was cut clean through with a saw. You will see a square hole in the concrete basement floor. Inside of the hole, a man dug out the form for the footing.... to support the post.... to support the beam.... to support the walls.... to support the roof!

Here's the hole!







Form installation

All the previous blog posts covered work that was done in the first week of work. We assumed that since the weather is so lousy and wet this week, that not much would get done. But we were wrong! The men want to get the foundation in so that the out-of-work carpenters can get started building the house. They are all appreciative to be working right now.

This blog post will cover the installation of the forms. Unlike when the footings were made, which used the excavated earth as a "form" to hold the concrete, the walls of the foundation use forms made out of boards. These boards are held together with fasteners. This first photo shows the blue guide line on which the forms will align to make the wall.



Here you can see the forms as seen from the Eddie and Park door. You can see inbetween the inside and outside pieces of board. There is more rebar in there to reinforce the concrete once it is poured.


Here is what the forms look like up close. Notice the fasteners that hold them together. All of it has to be strong to hold the wet concrete as it is being poured in.


Here is the wall of forms along the Peachtree side of the house.


This is the entry section of forms, as seen from inside the house's kitchen door. It is neat to see how each part of the plan is processed in order to construct the final product.




Footings in!

This is what the footing trenches look like before the concrete is put in. Notice the rebar laying in the trench, which serves to strengthen the concrete once it is poured.


This photo shows Mr. Williams and his employee directing where the concrete gets poured. The trough coming down into the trench is connected to a concrete mixer. Mr. Williams is making sure the river of concrete goes where it is supposed to go. The other man is spreading it down into all the spaces of the trench, for proper filling.



This is cool!!!!


This is where the main entry of the house will be. We call it the "front door" even though it is on the back side of the house.

Here the wet river of concrete is being smoothed out. What skill it takes to do each aspect of this construction. He made it look so easy.

Here we are the next day with Daddy- walking on the now-dry river of concrete. Linus is inspecting the job!

The family is standing where our new back "front door" will be.

Linus loves being on the work site, too!

Wednesday, November 11, 2009

Timber!!!!

This is the tree on the other side of the driveway. It was in the wrong place at the wrong time.

The "Pee-ing Tree" comes down

The pee-ing tree comes down in five minutes!!!!

(The cousins named it the pee-ing tree because it was so hollow, you could fill it up with water at the top, and it would "pee" out the side!)

Photos of footing trenches

We went by tonight to check in on the preparations that were made for the footings to be poured tomorrow, after the inspector comes by.  This is for the footings, not the foundation, which will sit on the footings.  Note the rebar down in the trenches.


Here is the area where the back entry will be:





Here's Chad "on top of the world!" on the dirt pile that was made by the digging of the trenches.

Demolition video footage

This is the raw video of the demolition just beginning. Zoe plans to make an actual movie of the entire demo/construction process. But that will be awhile in the making, as she collects footage.

Tuesday, November 10, 2009

Preparing Trenches


Mr. Williams is in the excavator preparing to dig trenches for the footings of the foundation to go in.  He had planned to pour the concrete tomorrow, but, alas, it will be Veterans' Day and no inspector is available to review the work first. So, now that is the plan for Thursday.

When you see the earth moved, and you realize that exact trench is there because of where you drew a line on your free-downloaded computer program, a bit of panic sets in! Yikes! I hope this looks as good in real life as it seems to on the computer.

This next photo is taken from the corner of Peachtree Ct. and Eddie and Park Rd.   It is my intention to take updated photos from this location, to show the progress as the house goes up.  The door on the side of the house used to be inside the breezeway.  This side of the house has probably never been exposed to the outside world!  Also, this photo shows the lack of the two silver maples which were on each side of the driveway.





Monday, November 9, 2009

Groundbreaking News!


Today, demolition began! The breezeway and garage were taken down in 36 minutes. It took *so* long, according to Mr. Williams, because he was taking his time, so as to not destroy any of the house that we are keeping.






Mr. Williams is our builder. He is very hands-on, and did all of the excavator work himself. (I think that's what the machine was called. You can look at the pictures for yourself to see.)



Also taken down were two mature silver maple trees. One was in really bad shape and needed to come down. The other one was in the wrong place at the wrong time! I was sad to see it go, as I really love the shadiness of the property.

Mr. Williams even let the boys each take a turn in the excavator. He let Conner and Duncan actually control it by pushing the levers to engage the drive and push the debris pile forward. They were so jazzed by that!

CONNER-

DUNCAN-
PETER-


You won't be surprised to learn that Zoe is our videographer for this project. She filmed an entire battery's worth of material. Some of it will be posted here for you to check out, for those of you who are interested in some live-action footage of the demolition.


INTRODUCTION

This blog is our effort to keep you informed of all the neat happenings going on over at Pipkin Place. We got our building permits from St. Louis County last Friday, and boy, were we excited! All this has gone from "idea" to "reality" in such a short time. According to my memory, it's been about 20 weeks since we had the idea to actively pursue addding on to the property.